On commercial projects plastering sits in the middle of the programme, between first-fix services and decoration. Getting it planned early keeps the trades behind it on schedule.
Sequencing
- Metal stud partitions and MF ceilings framed out.
- First-fix mechanical and electrical services installed and signed off.
- Boarding, then taping and jointing or skimming.
- Drying time before decorators start.
Documents we provide
For contractor-led work we supply RAMS (risk assessments and method statements), insurance certificates and any project documentation required for site induction. Sending the programme and site rules with the tender helps us return an accurate price.
Allow for drying
Drying time is the item most often squeezed. Building it into the programme — with heating and ventilation available on site — avoids decorating over damp walls and costly remedial work later.
Send us your drawings
Drawings, specifications and the programme let us measure accurately and confirm labour and timescales. Use the commercial enquiry form to upload documents directly.